The essentials

  • Adjudication is a formal statutory decision process, with a compressed preparation timetable.
  • The dispute must arise under a construction contract within the Act’s scope.
  • A respondent should act on receipt of the notice rather than wait for the full claim.
  • Payment decisions and rights-and-obligations determinations have enforcement consequences.
  • Budget for representation, technical evidence and adjudicator fees; winning does not automatically reimburse every cost.
Explore this guide 12 sections + FAQs

What construction adjudication is designed to do

Construction adjudication allows an independent adjudicator to determine a dispute arising under a construction contract. It is a formal process with statutory steps and a short timetable. It can address payment issues and other contractual disputes; it is not simply a meeting where a neutral person encourages compromise.

The speed is useful where unresolved payment or contractual questions threaten a project’s cash flow or progress. It also creates pressure: parties may need to organise records, legal arguments and technical evidence quickly. A claimant should prepare before starting, while a respondent should act as soon as notice arrives.

The broader guide to construction dispute options helps place adjudication alongside negotiation and other proceedings. Choosing the process should follow the problem. Identify the decision required, the parties involved and the evidence available before treating adjudication as the automatic next step for every building complaint.

Official resources: Building Performance — Mediation, arbitration and adjudication

Check the contract, parties and dispute

The first issue is whether the arrangement falls within the Construction Contracts Act and whether the proposed dispute arises under that contract. Read the complete contractual package, identify the parties’ correct legal names and establish what work or services were agreed. Older contracts and unusual arrangements may require particular attention to application and transitional rules.

Define the dispute precisely. A claim for an unpaid scheduled amount differs from a valuation dispute, a contested variation, a delay entitlement or breach of a residential implied warranty. Several issues can be connected, but an unfocused case makes jurisdiction, evidence and remedy harder to assess.

The payment claim and schedule guide explains the documents often central to a payment case. For a technical case, establish the contractual obligation and the alleged failure before commissioning broad reports. The adjudicator is deciding the referred dispute, so the notice, claim and requested outcome should describe that dispute consistently.

Official resources: Building Performance — Form 2 adjudication information

Compare adjudication with other available routes

Negotiation and mediation allow parties to design a settlement, including staged repairs, revised programmes or commercial concessions. An adjudicator instead makes a determination within the statutory framework. Arbitration and court proceedings have their own procedures, jurisdiction and consequences. None should be selected solely because it sounds less formal.

A Building Act determination is a separate MBIE process for matters within that Act’s scope. It should not be confused with a Construction Contracts Act adjudicator’s determination. Similar terminology does not mean the decision-makers can decide the same issues or award the same remedies.

Compare evidence demands, parties, cost, urgency and enforceability. A dispute involving several consultants and different contracts may need a broader strategy than a narrow claim against one contracting party. Court and other dispute-resolution options may be relevant where the desired outcome or parties do not fit a single adjudication.

Compare adjudication with other available routes
ProcessHow an outcome is reachedUseful question before choosing it
NegotiationParties agree terms directlyIs there enough information and authority to reach a practical deal?
MediationA mediator assists agreementCan both sides negotiate a remedy broader than a payment decision?
CCA adjudicationAn adjudicator determines a referred contractual disputeCan the claim and evidence be presented within the short timetable?
Arbitration or courtA tribunal or court decides within its jurisdictionDoes the dispute require a broader proceeding or more parties?
Building Act determinationMBIE decides matters within the Building Act processIs the issue one that this statutory process can determine?

Official resources: Building Performance — Mediation, arbitration and adjudication · Building Performance — Understanding determinations

The notice starts a process, not just a discussion

A notice of adjudication identifies the proposed dispute and initiates the statutory appointment process. It must satisfy the applicable requirements, including the prescribed information. Selection and appointment of an adjudicator should follow the Act and any relevant arrangements; a name printed in correspondence does not alone establish that appointment is complete.

A claimant should have the main evidence, chronology and calculation substantially ready before serving notice. Starting in order to create pressure and gathering the case afterwards can lead to rushed omissions. Confirm the correct parties, service details, relief sought and how the dispute has arisen.

A respondent should preserve the notice and delivery evidence, obtain the contract and identify who can give instructions. Inform insurers or other relevant advisers where notification may be required. Even before the full adjudication claim arrives, use the notice to begin gathering the records. Waiting for a more convenient stage can leave too little time for a meaningful response.

Official resources: Building Performance — Form 2 adjudication information

Understand the short statutory timetable

After the adjudicator’s notice of acceptance, the claimant generally has five working days to refer the dispute in writing. The respondent’s ordinary response period is five working days from receipt of the claim or notice of acceptance, whichever is later, subject to permitted extensions. Extension requests should be made promptly and supported with specific reasons.

Under section 46, the ordinary determination period is twenty working days after the response period ends. The Act allows thirty working days where the adjudicator considers further time reasonably required, and further time agreed by the parties. These rules do not mean every dispute finishes twenty days after the first notice.

Calculate each step using the relevant statutory working-day rules and verified service events. Ask the adjudicator to confirm procedural directions and any authorised extension in writing. A heavy workload or an informal request does not itself change a deadline. Build time for legal review, expert input and serving the complete bundle on all required recipients.

Official resources: Construction Contracts Act 2002 — Referral and response · Construction Contracts Act 2002 — Section 46 timing

Prepare a claim that answers the decision-maker’s questions

A strong claim explains the agreement, the relevant events, the disputed entitlement and the remedy sought. Use a concise chronology and a clear calculation. Link each proposition to a document or witness account. If claiming payment, reconcile the contract price, variations, prior payments, deductions and claimed balance so the adjudicator can follow the arithmetic.

Organise documents with consistent numbering and readable copies. Include the complete relevant clauses rather than isolated excerpts that conceal qualifications. Explain why a disputed instruction was authorised, why a valuation method applies or how a contractual notice was given. Assertions about unfairness cannot replace proof of entitlement.

For technical evidence of defects, choose an expert whose discipline fits the issue and ensure the report distinguishes observation from inference. A repair estimate should describe the proposed work and assumptions. Avoid introducing a large amount of loosely connected material simply to make the bundle appear comprehensive; it can obscure the evidence that matters.

Need help with your own situation?

Describe the issue and any important dates. Our introduction service is in early access; an enquiry does not appoint a professional or protect a deadline.

Ask about legal help

Respond to the claim and preserve jurisdictional objections

The response should identify what is admitted, what is disputed and why. Follow the structure of the claim so important points are not missed. Provide an alternative calculation where valuation is disputed, and explain the documentary basis for each reduction or different interpretation. An organised answer is more effective than a long narrative about the deterioration of the relationship.

Jurisdiction or procedural concerns should be raised promptly and specifically. Examples may involve the identity of the contracting parties or the scope of the referred dispute. Obtain advice on how to raise an objection while responding appropriately; simply declining to participate can leave the adjudicator deciding on the available material.

Where more time is needed, explain what evidence is required, why it matters and the proposed timetable. Continue preparing while the request is considered. Coordinate people who know the project with those presenting the legal case, so factual statements are checked rather than assembled from assumptions under deadline pressure.

What happens during the adjudication?

The process is often document-focused, but procedural directions may require further submissions, information or other steps. Read each direction carefully and keep a calendar of deadlines and service obligations. If a new issue arises, explain why it matters and seek the opportunity needed to address it, rather than assuming every late document will be accepted.

The adjudicator’s independence matters. Communications should follow the proper process and be copied as required; do not treat the adjudicator as a private adviser. Keep factual witnesses focused on what they observed or did, and experts focused on their professional analysis.

Settlement can remain possible while adjudication proceeds. If agreement is reached, document how it affects the proceeding, payment, fees and any remaining claims. A commercial discussion does not automatically withdraw the adjudication. Confirm the procedural position so one side does not stop preparing while the other expects the timetable to continue.

Official resources: Building Performance — Form 2 adjudication information

The determination has binding and enforceable consequences

A determination is binding even though the underlying dispute may later be revisited through an available court or other process. An application or disagreement does not automatically suspend compliance. Assess the actual determination, its payment dates or other requirements, and the available legal response immediately.

Current legislation distinguishes enforcement of payment determinations from determinations about contractual rights and obligations. Rights-and-obligations determinations are enforceable under section 59A; older summaries describing them as unenforceable should not be relied on without checking the applicable version and transitional position.

For enforcement and recovery questions, establish the route, required documents and deadlines. A determination is not money in the bank: the other party’s financial position and assets still matter. Conversely, a losing party should not ignore enforcement documents while planning a separate merits case. Obtain advice about compliance, any available challenge and whether a stay or other order is necessary.

Official resources: Building Performance — If things go wrong for contractors · Construction Contracts Act 2002 — Current enforcement provisions

Budget for the process and distinguish different costs

Adjudication costs can include legal representation, expert reports, document preparation and the adjudicator’s fees and expenses. The parties’ own costs and the adjudicator’s fees are separate categories under the Act. Do not assume that winning automatically requires the other side to reimburse the full legal bill.

The statutory costs rules include limited circumstances for an order relating to a party’s conduct. Fee allocation also needs attention. Ask the proposed provider or adjudicator about rates, deposits, administration charges and how fee arrangements are addressed. Settlement or withdrawal may still leave fees already incurred to be paid.

Request a staged estimate: initial assessment, claim or response, further submissions and post-determination work. Identify assumptions about expert involvement and document volume. A smaller disputed amount can still involve difficult technical evidence, so compare the likely cost with the practical value of the determination and realistic recovery.

Official resources: Construction Contracts Act 2002 — Costs and adjudicator fees · Building Performance — Form 2 adjudication information

Example: a final-account dispute with two different issues

Imagine a contractor claims a final balance that includes several variations. The owner accepts the original contract work but disputes the authority for two variations and says a retaining wall is defective. The hypothetical case contains both valuation and technical questions. Treating it as a simple unpaid invoice may miss the evidence needed for the wall.

Before initiating adjudication, the parties’ advisers identify the precise contractual dispute, compile instructions and payment records, and obtain a focused engineering opinion where appropriate. The claim explains the payment entitlement; the response addresses each variation and the alleged defect with an alternative calculation and supporting documents.

The adjudicator can then assess a defined dispute rather than reconstruct it from scattered messages. If a determination follows, the parties separately consider compliance and any remaining proceedings. The example illustrates preparation and issue selection; it does not predict which side would succeed or whether all associated claims could be resolved in the same process.

The first meeting and decision to proceed

Bring the complete contract, amendments, notice of adjudication if received, claim and schedule history, payment records, key correspondence and technical reports. Provide a short chronology and identify the outcome sought. State the earliest known deadline before discussing the full background so urgent procedural work can be prioritised.

Ask the lawyer to assess scope, strengths, evidence gaps, likely timetable and alternatives. Confirm whether the instruction covers a limited review, drafting, full representation or enforcement. If you are a contractor, consider the relationship between the adjudication and continuing site obligations; if you are an owner, consider access, safety and the effect on completion.

Before future projects, a commercial contract review can improve payment administration, variation authority and dispute clauses. It cannot eliminate every dispute, but clear records reduce the work needed to establish what was agreed. For the current dispute, leave the first meeting with a verified timetable, a defined evidence task and an agreed next decision point.

Frequently asked questions

Does the other party have to agree to adjudication?+

The Act provides a statutory right to refer qualifying disputes. It is different from a voluntary negotiation or mediation that depends on agreement to settle. Whether your particular dispute and contract fall within the Act must still be checked. The appointment and notice process also needs to be followed correctly.

Can a homeowner use construction adjudication?+

It can be relevant to residential construction disputes as well as commercial projects, subject to the contract, issue and applicable statutory provisions. Do not assume a homeowner is excluded simply because they are not a construction business. Equally, check that the proposed claim is against the correct party and arises under the relevant contract.

Is adjudication only for unpaid invoices?+

No. It can address disputes under construction contracts, including contractual rights and obligations. The exact scope and remedy need to be defined. A defect case may require technical evidence, while a missed payment-schedule case can turn on claim validity, service and deadlines. Different issues should not be treated as identical.

How long do I have to respond?+

The ordinary response period is short and runs from specified receipt events, with extensions available under the statutory process. Obtain advice as soon as the notice arrives rather than waiting for the final day. Confirm the operative deadline and any extension in writing, and prepare the substantive response while procedural questions are resolved.

Will there be a court-style hearing?+

Do not assume one. Adjudication is commonly driven by written material and the adjudicator’s procedural directions. The process may involve further information or other steps depending on the case. Prepare documents and witness or expert evidence to stand on their own rather than expecting to explain every missing point orally later.

Can I ignore the determination if I intend to sue?+

No. A separate proceeding does not automatically remove the determination’s binding effect or stop enforcement. Obtain prompt advice on compliance and any available challenge or stay. The immediate obligation and the eventual resolution of the underlying dispute are separate questions, each with its own procedure and timing.

Will I recover all legal costs if I win?+

That should not be assumed. The Act treats party costs and adjudicator fees separately and provides specific costs rules. Ask for advice on potential recovery and exposure before starting. Budget on the actual scope of representation and technical evidence, rather than treating a favourable determination as guaranteed reimbursement.

Can we settle after adjudication starts?+

Yes, a negotiated resolution may still be possible. Record payment or repair terms, treatment of the proceeding, fees and any claims left open. Confirm the procedural steps needed to end or pause the process. A conversation about settlement does not itself cancel deadlines or eliminate fees already incurred.

Official sources & further reading

  1. Building Performance — Mediation, arbitration and adjudication
  2. Building Performance — Form 2 adjudication information
  3. Construction Contracts Act 2002 — Referral and response
  4. Construction Contracts Act 2002 — Section 46 timing
  5. Building Performance — If things go wrong for contractors
  6. Construction Contracts Act 2002 — Current enforcement provisions
  7. Construction Contracts Act 2002 — Costs and adjudicator fees
  8. Building Performance — Understanding determinations
Updated 21 November 2026. This is general information, not advice about your circumstances. It has not been independently reviewed by a lawyer. Check current official information and obtain advice before relying on a deadline or taking a consequential step.