The essentials

  • An installer quotation, network approval and retailer export agreement answer different questions. Obtain each relevant document before relying on projected savings.
  • Installed generation capacity and permitted export capacity are different measures. Check the actual connection conditions for the site.
  • Specify equipment, commissioning, inspection, certification and responsibility for applications in the installation contract.
  • Compare outright ownership, finance and power purchase agreements over the full term, including roof work, property sale and early exit.
Explore this guide 10 sections + FAQs

1. Map the agreements before paying a deposit

Buying solar involves more than buying panels. The installation contract determines what is supplied and installed; the network process determines whether and on what terms the system can connect; the retailer agreement determines how imported and exported electricity is billed. The owner or occupier also needs authority to use the roof or land. A supplier may coordinate these tasks, but coordination should be written into its scope rather than assumed from a sales conversation.

Start with the intended outcome: lower daytime imports, export income, resilience, a commercial emissions objective or a combination. Ask which outcome is actually promised and which is a modelled estimate. A system described as battery-ready does not necessarily include a battery, and ordinary grid-connected generation should not be assumed to provide backup during an outage. Have a qualified installer explain the proposed design. Our energy law overview places these contracts alongside the wider electricity supply relationship.

1. Map the agreements before paying a deposit
Document or decisionMain questionCheck before commitment
Installation agreementWhat will be delivered and by whom?Equipment, exclusions, dates and acceptance tests
Network approvalHow may the system connect and export?Capacity limits, technical conditions and application status
Retailer export termsWhen and how will exported energy be paid?Rate, metering, start date and variation rights
Site permissionWho can use the roof or land for the project?Owner consent, lease duration and future access

2. Confirm roof, land and occupation rights

An owner should check the property's relevant restrictions and any approvals needed for the particular design. A tenant needs to consider the lease, landlord consent, reinstatement obligations and whether the tenancy or lease term is long enough for the proposed arrangement. In a unit-title or shared-roof building, identify who controls the installation area and maintenance access. A verbal indication that nobody objects is a weak foundation for equipment expected to remain for years.

Allocate responsibility for assessing roof condition and structural suitability before the installation price becomes final. Ask how the fixing method interacts with existing roof warranties, future maintenance and safe access. If the roof may need replacement during the system's life, price the removal and reinstallation responsibilities now. A property lawyer can examine site rights, while an engineer or competent technical specialist addresses the physical design; neither assessment replaces the other.

For a farm, commercial building or ground-mounted project, map cable routes, access, adjacent activities and any third-party land needed. Check the relevant council position for the actual works rather than relying on a general statement that solar usually needs no consent. Our property law hub is relevant when installation rights must survive a sale, lease assignment or change of occupier. Ensure the contractual customer has authority to grant the access being promised.

3. Check the current distributed-generation connection process

The Electricity Authority identifies Part 6 of the Electricity Industry Participation Code as the framework for connecting distributed generation to local networks. The applicable route depends on the system and current rules. Ask the local distributor which application process applies, which documents are required and what approvals remain outstanding. An installer saying that it has submitted an application is different from the distributor approving the installation subject to specified conditions.

The Code has been amended during 2026, including provisions concerning export limits and application assessment. Use the current Part 6 and the distributor's current published requirements rather than an old installation checklist. Do not assume a universal processing period or a single export allowance for every property. Ask the designer to identify both total generation capacity and proposed maximum export, and record the inverter configuration on which the application relies.

Make the installation agreement address an unfavourable connection outcome. Possible commercial choices include redesign, accepting a lower export level, paying for an upgrade or cancelling before equipment is ordered. Identify who bears application and design costs in each case. A condition that simply says 'subject to approval' can leave uncertainty about deposit refunds, the deadline for deciding and whether the customer must accept a more expensive alternative.

Official resources: Electricity Authority: current Part 6 distributed-generation framework · Electricity Authority: distributed generation

4. Understand export limits and operational conditions

The amount a system can generate is not necessarily the amount it may export. Ask for the network's approved limit and any conditions affecting operation, control or later changes. Have the supplier model the project using those conditions. A quotation based on exporting all surplus generation may overstate the result if the network approval permits less. This is a design and contract issue to resolve before relying on a payback figure.

Request a plain-language explanation of any export-control equipment, remote-control function or proposed curtailment arrangement. Identify who configures it, maintains it and bears the consequence of incorrect settings. Ask whether adding panels, changing an inverter or installing a battery later requires a further approval or notification. The answer should come from the actual approval and applicable rules, not an assumption that one approval covers every future alteration.

Where a network assessment is disputed, obtain the reasons, relevant study and the available review or dispute route under the current framework. Preserve the original design and each revised proposal so the disagreement is traceable. Distinguish challenging a condition from simply preferring a larger export entitlement. A specialist can evaluate whether the technical and legal basis has been properly applied without promising that the network must accept the customer's preferred capacity.

Official resources: Electricity Authority: solar power and network connection

5. Turn the quotation into a complete installation scope

List the proposed panels, inverter, battery if any, mounting system, monitoring service and significant electrical work. State whether substitutions require written approval and what standard of equivalence applies. Include scaffolding, roof work, switchboard changes, meter work, inspection and application fees in either the price or a clear exclusions schedule. This makes it possible to compare quotations that otherwise appear to offer the same system at very different prices.

Define payment milestones by completed work or agreed deliverables. Ask what happens if equipment arrives late, the network requires redesign or the roof assessment reveals additional work. A variation should identify the change, price and effect on completion before it is carried out, subject to any genuinely urgent safety issue. Keep salesperson claims about output, savings and backup capability with the contract so there is a record of what informed the purchase.

For a household purchase, applicable consumer protections may be relevant to the quality of goods, services and representations. Commercial contracting requires its own analysis of the parties and terms. Our consumer law information explains the general distinction between a product problem and a service failure. If the dispute concerns building work or a substantial installation variation, the construction disputes hub can help identify the separate contractual issues.

  • Record exact equipment or an agreed substitution process.
  • Assign every approval and inspection task to a named contracting party.
  • State when risk, ownership and maintenance obligations transfer.
  • Define completion by commissioning and required handover documents.

Need help with your own situation?

Describe the issue and any important dates. Our introduction service is in early access; an enquiry does not appoint a professional or protect a deadline.

Ask about legal help

6. Require electrical certification and a usable handover

Electrical work must be dealt with by appropriately authorised people. The Electrical Workers Registration Board explains that grid-connected PV work involving a mains inverter is high-risk prescribed electrical work requiring certification and a record of inspection. Ask the contractor which certificates and inspection records are required for your system and who will provide them. Do not treat a sales invoice or a monitoring-app screenshot as a substitute for the relevant electrical documentation.

Agree a handover pack containing the as-installed equipment list, relevant plans, commissioning results, network approval, certification, warranty contacts and operating instructions. Have the installer demonstrate normal operation and explain who to contact if the monitoring system reports a fault. You should not be expected to carry out unsafe diagnostic work. Keep the pack available for future maintenance, insurance questions and a property transaction.

Write an acceptance process that separates minor outstanding items from a material inability to operate as agreed. Record any unresolved defect and the proposed remedy date. If payment is disputed, check the contract and obtain advice before withholding a sum; an indiscriminate refusal can create a separate debt dispute. The aim is to identify which promised deliverable is missing and the proportionate contractual response, while ensuring that unsafe equipment is assessed promptly by a qualified professional.

Official resources: Electrical Workers Registration Board: certification paperwork · WorkSafe: solar installation safety

7. Confirm export payments and metering separately

Network permission to export does not itself specify what a retailer will pay. Obtain the export agreement and confirm the rate structure, start date, required meter configuration and any conditions relating to the customer's import plan. Ask whether the rate is fixed or variable, how changes are notified and whether credits are paid out or offset against imported electricity. A rate shown in a sales model is not a binding retailer commitment unless the relevant agreement makes it one.

Check who arranges the meter change or configuration, who pays and what evidence confirms completion. Note the date when exports become eligible for payment. Keep commissioning records and the first bills so missing credits can be traced to generation, metering, registration or account processing. Avoid assuming that all generation shown in an inverter app equals export: some energy may have been consumed at the property before reaching the meter.

EECA notes that retailer buy-back rates vary and network agreements can limit export. For a billing disagreement, compare exported units and the applicable rate rather than simply comparing total solar production with the credit. Our electricity billing dispute guide provides a complaint sequence for missing or incorrect credits. Ask the retailer for the underlying export data and the contractual explanation for any excluded period.

Official resources: EECA: commercial solar and purchase arrangements

8. Compare ownership, finance and power purchase agreements

With an outright purchase, the customer generally pays for the system and takes the agreed ownership and maintenance responsibilities. Finance adds repayment and security terms that must be read alongside the installation agreement. Under a power purchase agreement, an energy supplier may fund and own the equipment while the customer commits to purchasing electricity. The label does not settle the detail: identify who owns each asset and which contract governs performance and payment.

For a PPA, examine duration, price changes, minimum purchases, access rights, insurance, maintenance, failure to generate and early termination. Ask what happens when the business closes, the tenant leaves, the roof needs major work or the building is sold. A low initial payment can be accompanied by a substantial long-term commitment. The property owner, occupier and funder may need compatible agreements so that an energy contract does not promise site access that the customer cannot provide.

Our commercial electricity contracts guide explains how a PPA interacts with wider electricity procurement. Ask for a financial comparison using the same assumptions about demand, export, maintenance and contract duration. Have an adviser test the consequences of lower usage or a shorter occupation period. This is especially important where a model assumes the business will consume nearly all daytime generation for many years.

Official resources: EECA: commercial solar and purchase arrangements

9. Distinguish an equipment fault from a savings disagreement

A system can generate electricity correctly and still deliver lower monetary savings than a sales forecast. Start by comparing the promised specification with what was installed, then compare measured performance with the assumptions used in the forecast. Weather, shading, consumption timing, tariff changes and export restrictions may affect the result. Ask an independent technical specialist to identify the cause where the supplier's explanation is disputed.

Keep product warranties, workmanship commitments and any express output or savings promise separate. Identify the party responsible for each. A panel manufacturer's warranty may not cover installation damage, the cost of access or a retailer's change in buy-back rates. Request the remedy that matches the actual problem: repair, completion of omitted work, correction of settings, a contractual adjustment or compensation supported by evidence.

Consider a hypothetical shop that was sold a system on the assumption it would use most generation during weekday trading. If it later changes to evening-only operation, lower savings may reflect the new demand pattern. If the installer instead supplied a materially smaller inverter than agreed, that raises a different contractual question. A clear baseline prevents the dispute from becoming a general argument about whether solar is worthwhile.

10. Plan for repairs, property sale and contract exit

Record maintenance responsibilities, service access, monitoring charges and ownership of operational data. Ask whether a remote service is required for basic system operation and what happens if the supplier stops providing it. For equipment financed or owned by another party, identify any consent needed before sale, removal or alteration. Include those documents in property due diligence so a buyer does not assume that every item fixed to the roof transfers free of obligations.

Before signing an exit or settlement document, calculate remaining payments, removal costs and the value of any equipment transfer. Confirm how roof penetrations and damage will be made good. A termination right in one agreement may not end related finance, export or site-access commitments. Obtain advice where the agreements are linked or the proposed release covers more than the installation dispute.

A useful legal review bundle includes the quotation and sales model, signed contracts, site permissions, connection application and decision, electrical handover pack, bills and a short explanation of the unresolved issue. Ask the lawyer to identify the decision that must be made next and any time-sensitive notices. Technical and legal advice work best together when each specialist can see the same as-installed system and contract version.

Frequently asked questions

Does an approved solar quotation mean the network has approved connection?+

No. A quotation describes the supplier's proposal, while the distributor's connection process addresses the local network. Ask for the actual application status and written decision, including conditions. Your contract should say what happens if approval requires a different design or additional expenditure before equipment is ordered.

Can I export everything my panels generate?+

Not necessarily. Some electricity will be used on site and the permitted export level may be lower than the system's generation capacity. Check the approved configuration and operating conditions. Ask the supplier to model financial outcomes using that limit rather than assuming unrestricted export at a constant rate.

Who pays for network upgrades or meter changes?+

Check the network terms, retailer requirements and installation scope. Ask for each cost to be included or clearly excluded before signing. If the final requirement is unknown, agree an approval process and a spending limit or cancellation option; otherwise the parties may disagree about whether an unexpected cost was already included.

Will my panels keep the house powered during an outage?+

Do not assume so from the presence of panels or the phrase battery-ready. Ask a qualified installer what the specific design can supply during an outage, which circuits are supported and what additional equipment is included. Record any promised backup capability in the specification and request an appropriate demonstration at handover.

What documents should I receive when installation finishes?+

Ask for the applicable electrical certificates and inspection records, network approval, equipment details, commissioning information, warranties and operating instructions. Confirm that the export-metering arrangements are complete separately. Keep this pack with the property records; it helps future maintenance and avoids relying entirely on the original sales contact.

Is a power purchase agreement the same as buying a solar system?+

No. A PPA can leave ownership with an energy supplier while committing the customer to buy electricity over time. Examine price adjustment, minimum purchase, access, maintenance and exit provisions. Compare the full arrangement with ownership or finance, particularly if the building might be sold or the occupation period is shorter than the contract.

What if the system produces less than the sales estimate?+

Identify whether the estimate was a contractual promise and which assumptions it used. Compare the installed equipment, actual generation, shading, usage and tariff with that baseline. A technical fault, an inaccurate sales representation and a change in your consumption pattern can require different evidence and remedies.

Can I transfer the solar agreement when selling my property?+

Transfer depends on the relevant agreements and ownership arrangements. Check finance, PPA, site-access and retailer terms rather than assuming the buyer automatically takes over. Raise the issue before committing to the sale, and document any required consent, repayment, assignment or equipment removal in the transaction.

Official sources & further reading

  1. Electricity Authority: current Part 6 distributed-generation framework
  2. Electricity Authority: distributed generation
  3. Electricity Authority: solar power and network connection
  4. Electrical Workers Registration Board: certification paperwork
  5. WorkSafe: solar installation safety
  6. EECA: commercial solar and purchase arrangements
Updated 21 November 2026. This is general information, not advice about your circumstances. It has not been independently reviewed by a lawyer. Check current official information and obtain advice before relying on a deadline or taking a consequential step.