The essentials
- A valid Construction Contracts Act payment claim can have consequences beyond an ordinary invoice.
- The contract may set the schedule deadline; twenty working days is the fallback when it does not.
- A payment schedule needs an amount and, if reduced, a calculation and reasons.
- Check service and the applicable working-day definition rather than counting ordinary weekdays.
- A defect complaint or negotiation does not automatically replace a timely payment schedule.
Explore this guide 12 sections + FAQs
Received a payment claim? Identify the clock immediately
A construction payment claim should be reviewed as soon as it arrives, even if you have already complained about the work. Save the entire message, attachments and delivery details. Identify the contract, sender, claimed amount, payment due date and any accompanying information sheet. Forward the complete package to the person responsible for the project and legal advice.
The immediate questions are procedural and substantive. Was a valid claim served under the Construction Contracts Act? When is a response required? What amount is actually accepted? A dispute about workmanship does not answer the first two questions. Waiting for a site meeting can leave the payment process moving without a response.
Seek construction dispute legal help promptly where a deadline is close or the amount is significant. This does not require abandoning commercial discussions. It means protecting the formal position while the parties investigate and negotiate. Keep an explicit distinction between correspondence about repairs and the document intended to respond to the payment claim.
Official resources: Building Performance — Form 1 information accompanying payment claims
Payment claim or ordinary invoice: examine the content
A payment claim under section 20 must be written, identify the contract, work and relevant period, state the amount and payment due date, explain its calculation and state that it is made under the Act. It must also be accompanied by the prescribed response information. An invoice may serve this function if the requirements are met; the document’s label alone does not decide the issue.
Conversely, calling a document a payment claim does not automatically make it compliant. Check the whole package, the contract and service. Where validity is uncertain, obtain advice and consider a protective response rather than betting the entire position on an assumed technical defect.
For the contractor, clear supporting detail reduces unnecessary disputes. Show the work claimed, prior payments, variations and adjustments so the payer can understand the amount. The statutory mechanism is not a licence to claim sums without a contractual basis. A later dispute may still examine whether the work was done and how it should be valued.
| Document | Purpose | What it should not be confused with |
|---|---|---|
| Ordinary invoice | Requests payment under the commercial arrangement | Automatically a compliant statutory payment claim |
| CCA payment claim | Invokes the statutory claim process when requirements are met | A final determination that all claimed work is payable |
| Payment schedule | States the payer’s response and scheduled amount | A general complaint without a clear amount and reasons |
| Defect notice | Identifies problems and seeks an appropriate repair response | A substitute for every payment schedule |
| Adjudication claim | Presents a dispute to an appointed adjudicator | The original invoice or payment claim |
Official resources: Construction Contracts Act 2002 — Payment claims and schedules
Find the contractual deadline before using the fallback
The time for providing a payment schedule is the time required by the construction contract. If the contract does not provide for it, the fallback is twenty working days after service of the payment claim. A contract can therefore require a response sooner than someone expects after reading a general article.
Do not confuse the schedule deadline with the payment due date. Record both separately and identify the clauses used to calculate them. Look at the complete contract package, including special conditions and incorporated documents. A standard form may have been amended, and a project administrator’s usual practice may differ from the actual terms.
Prepare a dated timeline showing service, response and payment events. Ask someone to independently check the calculation where the consequences are substantial. If the payer needs technical information before finalising a response, request it promptly while continuing to work towards the existing deadline. An unanswered request for clarification does not, by itself, extend the statutory or contractual timetable.
Official resources: Construction Contracts Regulations 2003 — Prescribed forms
Service and working days require their own check
The deadline depends on when and how the document was served. Retain the original email, postal information, courier record or other delivery evidence and check the Act and contract’s service provisions. Do not assume that sending to a site supervisor, an old address or a shared inbox is necessarily sufficient in every case.
The Act’s working-day definition excludes specified weekends and holidays and uses different summer exclusions for different provisions. For the relevant payment and many adjudication provisions, the exclusion runs from 24 December through 5 January. Certain court review and enforcement provisions use a different period. Regional anniversary days and observed holidays can also matter.
A normal calendar reminder is therefore only useful after the legal calculation has been checked. Identify the relevant provision and location, rather than using one generic “business days” calculator for every step. If service is disputed, record both possible dates and obtain advice urgently. Do not wait until the last arguable date while assuming the other party accepts your calculation.
Official resources: Construction Contracts Act 2002 — Working-day definition and provisions · Construction Contracts Act 2002 — Current Act
What a useful payment schedule contains
A schedule must be written, identify the claim and state the amount proposed for payment. Where that amount is lower than claimed, it must explain the calculation and reasons for the difference, including reasons for withholding payment. A scheduled amount can be zero, but the response still needs a properly explained basis.
Build the schedule around the claim’s line items. For each disputed item, identify the amount accepted, the amount disputed and the reason. Examples might include a variation whose entitlement is disputed, work not yet completed or an incorrect quantity. The reason should connect the facts with the contractual position rather than merely express dissatisfaction.
Attach relevant photographs, measurements, approvals or correspondence where useful, and label them clearly. Avoid burying the actual response in a large document dump. A reviewer should be able to reconcile the claimed amount to the scheduled amount without guessing. Check that the arithmetic, GST treatment and prior payments are consistent across the schedule and attachments.
Official resources: Construction Contracts Regulations 2003 — Prescribed forms
Support reductions with a disciplined project record
Different objections need different evidence. An incomplete-work dispute may need a progress assessment. A quantity dispute may need measurements and the agreed rate. A variation dispute may turn on instructions, authority and the contract’s approval process. A defect allegation may require an independent technical opinion and a realistic repair scope.
Use a claim register that records each payment claim, schedule, payment and variation. Keep original documents and note who made key decisions. When several people communicate with the contractor, inconsistent instructions can undermine the explanation of what was authorised. Agree a single route for formal responses while preserving the underlying site records.
The guide to documenting defective or disputed work explains the separate investigation process. Do not invent a deduction because an exact repair quote is unavailable. Explain the basis actually relied on and obtain advice about presenting uncertainty. A supported estimate and a clear factual explanation are more useful than an unexplained round-number withholding.
Need help with your own situation?
Describe the issue and any important dates. Our introduction service is in early access; an enquiry does not appoint a professional or protect a deadline.
Ask about legal helpWhat happens if no schedule is provided in time?
Where the statutory conditions are met and no timely schedule is provided, the payer can become liable for the claimed amount on the due date. The Act provides debt-recovery consequences, and its special recovery rules restrict reliance on counterclaims or set-off in those proceedings. This is why a genuine underlying dispute does not justify simply ignoring the claim.
A late objection may still be relevant to a separate substantive dispute, but it does not automatically reverse the consequences of missing the schedule deadline. Promptly check validity, service, timing and the available response to any demand or proceeding. Do not assume that sending the schedule late has cured everything.
For recovering an unpaid construction amount, distinguish entitlement from collection. A contractor needs evidence of the claim, service, due date and amount unpaid. The payer needs to understand the particular legal route being used. Insolvency threats or enforcement steps deserve immediate advice; they should not be treated as another routine invoice reminder.
Official resources: Building Performance — Form 1 information accompanying payment claims · Construction Contracts Act 2002 — Current Act
A schedule does not end the payment dispute
A timely schedule states the payer’s position; it does not require the contractor to agree with it. The contractor may dispute the deductions or seek a determination through an available process. Equally, stating an amount in the schedule creates an immediate practical question about paying that amount by the applicable due date.
Separate undisputed payment from the disputed balance when discussing resolution. Keep payment references clear and record what each transfer relates to. If the parties negotiate instalments or a compromise, document whether that changes the due date, settles particular issues or leaves other claims open. Ambiguous “full and final” messages can create a new dispute.
The guide to construction adjudication explains a formal route for disputes under construction contracts. Before choosing it, identify whether the case concerns an unpaid scheduled amount, a missed schedule, valuation, variations or defects. Those questions overlap commercially but may require different evidence and legal arguments.
Suspending work requires a proper legal basis
The Act allows suspension in specified non-payment situations, subject to notice and waiting requirements. Section 24A includes a five-working-day period after the relevant notice before the statutory right can be exercised, where its conditions are satisfied. An unpaid invoice does not make immediate abandonment of the site automatically lawful.
A contractor should check the triggering circumstances, notice content, service and timing before stopping. A payer receiving a suspension notice should assess it promptly rather than assume it is merely negotiating pressure. Both parties should consider site security, weather protection, safety, materials and programme effects while preserving their legal positions.
Distinguish suspension from termination. They have different purposes and consequences, and a contract may contain additional provisions that need coordinated advice. If a payment plan or standstill is agreed, put the exact arrangements in writing. An informal promise to “sort it out next week” is a poor foundation for deciding whether a statutory notice remains active.
Official resources: Construction Contracts Act 2002 — Suspension of work
Example: a homeowner disputes a variation and workmanship
Imagine a homeowner receives a payment claim covering an agreed progress amount and a bathroom variation. The homeowner says the variation was never approved and points to uneven tiling. Those hypothetical concerns should be investigated, but a message saying “I am unhappy and will not pay” may fail to provide the clear statutory response needed.
A better process identifies the claim and deadline, reviews the variation instructions, assesses the work and states a reasoned scheduled amount. The schedule explains the disputed variation separately from the workmanship concern and includes the evidence available. Any accepted amount is addressed on its own due date.
The contractor can then assess the actual objections, provide missing records, negotiate or pursue a formal determination. Neither side has to pretend the dispute is resolved. The improvement is that the payment position, factual disagreement and repair request are understandable, instead of being mixed into an emotional email chain with no clear amount or timetable.
Set up payment administration before the first claim
A project should identify who receives claims, who checks work, who approves variations and who sends schedules. Set up cover for leave and holidays. A claim sitting in an accountant’s inbox while the project manager is away can create consequences unrelated to the quality of the work.
At contract stage, review claim dates, response periods, valuation methods, retention arrangements and service addresses. The broader business contract review guide explains why incorporated documents and special conditions need attention. Construction payment provisions deserve their own review because they interact with the Act rather than operating only as ordinary invoice terms.
Use consistent templates, but require the person completing them to address the actual claim. A template saying “all rights reserved” does not provide missing reasons or arithmetic. Periodically reconcile the contract sum, approved variations, claimed totals and payments. This catches errors early and gives both parties a clearer basis for forecasting cash flow.
Legal scope, costs and documents to provide
The cost of advice depends on urgency, the quality of the contract and records, claim complexity and whether expert valuation or court work is needed. A focused review of one claim differs from preparing an adjudication or defending debt proceedings. Ask for the initial task to be defined: deadline assessment, schedule preparation, merits advice or recovery strategy.
Send the signed contract and amendments, claim package, proof of receipt, previous schedules, payment history, variation records and main technical evidence. State any known deadline and whether proceedings or a suspension notice have arrived. Do not spend days perfecting a chronology before alerting the adviser to an urgent response date.
The first practical outcome should be a verified timetable and an action plan identifying what must be sent, by whom and how. After that, develop the evidence for the underlying dispute. This sequencing protects the immediate position without confusing a quick procedural response with a complete assessment of every construction issue.
Frequently asked questions
Can an invoice also be a payment claim?+
Yes, if it satisfies the statutory requirements and is properly served with the required accompanying information. The title “invoice” does not prevent that result. Conversely, a heading saying “payment claim” does not cure missing requirements. Review the whole document package and contract rather than deciding from the subject line.
Do I always have twenty working days to respond?+
No. The construction contract may specify the response time. Twenty working days is the fallback where it does not. Check the contractual terms and service date promptly. Record the schedule deadline separately from the payment due date, and use the applicable working-day rules rather than ordinary calendar days.
Can I schedule zero?+
A zero scheduled amount is possible, but it still needs the required written response and reasons. Explain the calculation and the basis for withholding the claimed sum. Simply stating that you refuse to pay because you are dissatisfied may leave important requirements unanswered and makes the underlying dispute harder to evaluate.
Does a defect list count as a payment schedule?+
Not automatically. It may explain problems without identifying the relevant payment claim or stating a scheduled amount and calculation. Treat the documents as serving different functions. A lawyer can assess whether existing correspondence meets the requirements, but it is safer to prepare a clear, claim-specific response before the deadline.
What if the builder has not supplied the information I requested?+
Keep the request and follow up, but do not assume it stops the response clock. Work with the information available and obtain advice on the appropriate schedule and any validity issues. Record what is missing and why it affects the valuation, rather than waiting silently for a complete file.
Can I challenge the work after missing the schedule deadline?+
A substantive dispute may remain, but the missed deadline can create immediate payment consequences under the Act. A later claim is not necessarily a defence to the statutory recovery route. Obtain advice on both issues separately: the payment liability now being asserted and the evidence and process for the underlying construction claim.
Does sending a schedule mean the contractor must accept my deductions?+
No. It records your position and can preserve a dispute for the appropriate process. The contractor may challenge the amount through negotiation, adjudication or another available route. Keep supporting evidence and address any scheduled payment on time. A schedule is a procedural response, not a final ruling on entitlement.
Should a contractor stop work as soon as payment is late?+
Not without checking the legal basis and required steps. Statutory suspension has conditions, notice and timing requirements, and contractual provisions may also matter. Consider site safety and protection while obtaining advice. Suspending and terminating are different actions, so use the correct process for the intended result.
Official sources & further reading
- Construction Contracts Act 2002 — Payment claims and schedules
- Building Performance — Form 1 information accompanying payment claims
- Construction Contracts Regulations 2003 — Prescribed forms
- Construction Contracts Act 2002 — Working-day definition and provisions
- Construction Contracts Act 2002 — Suspension of work
- Building Performance — Other Construction Contracts Act requirements
- Construction Contracts Act 2002 — Current Act